|
Animation |
When enabled, actions taking place during each step are animated.
When not enabled (default), you will only see a static
representation of the objects, or the sub-set of the same, you have
opted for in this dialog box. |
|
Step size |
This option enables you to change the simulation rate for each step.
By altering the numbers, you can make the sub-steps smaller or
larger, which makes the simulation run more slowly or quickly.
Step Size is only available when the Animation
check box is selected. |
|
[s] |
This box shows the amount of time elapsed in the process from the
process's start to the current activity. |
|
Hide Unassigned Parts |
Selecting this check box hides all items that are unassigned to
activities (that is, items in the product list; this option does not
affect parts that are in the resource list). For more
information on how this option affects product visibility, see
Product Visibility in Process Verification. |
|
Keep Assembly State after closing PV |
If the check box selected, then the visibility state of all parts
remains. If the check box is not selected, then the
visibility state of all parts is restored to the states that they
had before starting process verification. See also
Examples of Process Verification |
|
Cross-Highlight |
If this check box is selected, cross highlighting occurs for objects
that have been linked to processes by means of relations. The
objects affected by the cross highlight are highlighted and every
process is separately displayed step-by-step in both the PPR tree
and 3D graphic views.
The following assigned objects can be cross highlighted:
-
processes
-
products
-
resources
-
manufacturing assemblies and manufacturing kits
-
FTA objects and geometric elements linked to an FTA object.
When the Cross highlight check box is selected, the
Cross highlight options button becomes available. For a
more complete discussion of this dialog box and the cross
highlighting options, see
Cross Highlighting for Process
Verification. |
|
Hide Unassigned Resources |
Selecting this option hides all unassigned resources. |
 |
Licensing
|
|
|
The Show Welds check box appears only if
you have license for the DPM Fastening Process Planner product. |
|
Show Welds |
Selecting this check box allows you to see the
effects of weld assignments in the 3D geometry. The information is
provided by colors:
- Green: a weld is consumed (i.e., assigned). Green appears under
these conditions:
- If the Show Weld option is off and the weld is assigned to
any activity
- If the Show Weld option is on and it is assigned to any
activity other than the current activity.
- Red: the weld is consumed by the current activity. A weld is
red if the Show Welds check box is on and it is assigned to the
current activity.
- Default color (set to yellow, initially): the weld is not
consumed (i.e., it is not assigned to any activity).
When you do not select the Show Welds check box, the
welds are not highlighted in any activity. |
|
Active Window for Switch |
If you have a switch activity and you select this option,
the Select Next Activity dialog box appears, which
enables you to select the activity you want to see.

If you do not have this option selected, the default next
activity appears. |
TSA Products
Shown/Hidden
(For information on how these selections are affected by the
Hide Unassigned Parts option,
see Product Visibility in Process
Verification.) Please note the following:
- The process verification visibility options are independent
from the visibility status of a product or
resource before starting process. If a product/resource is in
hide mode before starting process verification, it can be be set
to show mode while process verification is running.
|
|
Hide Products |
This option hides all products assigned to any of the activities.
|
|
Show TSA's Products |
This option shows only the products assigned to the TSA, the
preceding activities, and all products not assigned to any activity
(unless you selected the Hide Unassigned Parts check box,
as described above).
This option is best explained with an example. The
assumptions for this example are:
- Part A (assigned to Activity 2)
- Part B (assigned to Activity 3)
- Part C (unassigned)
- Hide Unassigned Parts check box is clear (i.e.,
unassigned parts are shown)
When Process Verification shows you:
- Activity 1, you see only Part C, the unassigned part.
- Activity 2, you see Part A, which is assigned to that
activity, plus Part C.
- Activity 3, you see all the parts: Part A, from the
preceding (second) activity, Part B, from the third activity,
and Part C because it is unassigned.
If you have select the Hide Unassigned Parts check
box, you see Parts A and B associated with the activities as
described above, but you do not see Part C.
The relation type Process removes product
removes the product from the process and sets its visibility status
to hidden as long as it will be reassigned with
process processes product.
|
|
Show All Products |
This option enables you to see all the products assigned to any of the
activities. |
|
Show Current TSA's Products |
This option enables you to see only the products assigned to the
current TSA. |
|
TSA's Resources
Shown/Hidden |
|
Hide Resources |
This option hides all resources assigned to all of the activities. |
|
Show Activity's Resources |
You see only the resources associated with the active activity and all
resources unassigned to any activity. Behavior for the different
types of relations:
- Process runs on resource: here the resource is
only seen at the activity to which it is assigned.
- Process uses resource: here the resource is only
seen at the activity to which it is assigned.
- Process attaches resource: here the resource is
seen at the activity to which it is assigned and at all
succeeding activities until the resource is detached with
Process detaches resource.
- Process detaches resource: here the resource is
hidden at the activity to which it is assigned and at all
succeeding activities until the resource is reattached with
Process attaches resource.
|
|
Show All Resources |
You see all the resources. |
|
Reframe |
|
Reframe All Items |
The 3D geometry is reframed with each new step. The reframing is
centered on the center of the items as a group. |
|
Reframe Off |
the 3D geometry is not reframed, even when the effects of the process
put some items beyond viewing range. |
|
Reframe Activity's Items |
The 3D geometry is reframed with each new step. The reframing is
centered on the center of the items used in the activity only.
Therefore, if a specific activity involves moving a handle away from
a reel, then the center of the reel and handle, looked at as a
single entity, is the center of the frame. |
|
State
Management |
- When the State Management check box is selected, if
the user wants to start Process Verification at a
specific activity, Process Verification synchronizes to
the start condition of that activity before executing the details
(assuming that there is a start condition defined for that
activity). Navigating through each activity executes the start
condition of the activity before executing the details.
-
When the State Management check box is not selected,
only the details are executed for each activity. By
enabling/disabling this option, you can decide whether you want to
apply the start condition for each activity.
|
|
Apply End Condition |
When the Apply End Condition check box is selected,
Process Verification synchronizes to the end condition of that
activity before executing the details (assuming that there is a end
condition defined for that activity). Navigating through each
activity executes the end condition of the activity before executing
the details.
|