Equipment and Systems
design is based on work packages. Each work package is created directly
under the PRC. During 2D/3D schematic driven routing, the schematic
documents are inserted directly underneath the PRC and not underneath the
work packages. |
 |
You cannot select a
P&ID in the schematic browser while schematic routing. In the schematic
mode when you click Route a Run, the Open Schematic Diagram
option is unavailable. |
 |
1. |
Create the schematic documents. (e.g. TEST_PID1, TEST_PID2 and so on). |
|
2. |
Insert the schematic documents under the root (PRC). |
|
|
Product structure is as follows:
PRC (or Root document for file based)
|
|
| ------ > TEST_PID1 (Inserted directly under the PRC)
|
| ------ > TEST_PID2 (Inserted directly under the PRC)
|
| ------ > TEST_PIPIING WORKPACKAGE1
|
| ------ > TEST_PIPIING WORKPACKAGE2
|
| ------ > TEST_EQUIPMENT_ WORKPACKAGE1
|
| ------ > TEST_EQUIPMENT_ WORKPACKAGE2
|
 |
Note: You can drag and
drop the schematic documents to insert them into the PRC.
In case of file based scenario, the schematic documents are inserted under
the root document. |