 |
This procedure describes how to add activities to a process from a set of process
libraries. This procedure has the following sections:
Create Logical Activities
|
|
To perform this procedure:

OK button
The activity is added
by clicking OK, which closes the dialog box.
Apply button
Apply is
used to add the activity; the dialog box remains opened, which allows
you to add
additional activities.
Cancel button
Cancel
closes the dialog box and voids any activity additions that occurred
while the dialog box was opened, with the exception of activities you
have already added by using Apply.
|
|
Either of two methods can be used to add activities to a process. These include:
|
|
Insert Activities Using the User-Defined Activities Toolbar
|
|
-
Select the activity to be created by clicking one of the icons in the toolbar or one of
the User Defined Activities menu items.
-
Select an existing activity (or the top-level Process node) in the PPR tree.
-
The newly added activity becomes a child of the selected activity.
-
If a PERT chart is open, an activity can also be selected in that viewer as
the parent of the newly created activity.
|
 |
Using the commands in a User Defined Activities toolbar (or
Insert > User Defined Activities menu) allows only for the creation of activities of the selected type in a hierarchical mode. |
|
Due to this constraint, using the User Defined Activities
toolbar is not the most flexible method for adding activities to a process.
Insert Activity
(described in the next section) is recommended for the most
flexibility. |
|
Insert Activities Using the Insert Activity Command
|
|
Insert a
Child Activity with Another Activity as Parent
|
|
-
Click Insert Activity
in the
Activity Management toolbar to display the
Insert Activity dialog box.
-
On the PPR tree (or in a PERT chart), click on the
activity (including the top-level Process node) that you want to be the parent of
the activity.
-
In the Insert Activity dialog box, click Add as Child, if necessary (it is selected by default).
-
In the left column, select the activity to be added as a
child activity of the parent selected above.
-
Click Apply (if you wish to add more
activities) or OK (if you want the Insert Activity dialog box
to close).
The activity selected becomes the child of the parent
activity selected. |
 |
- The activity selected in this example, Open_Clamp.1, could have been selected inside a PERT chart,
if the PERT chart were open.
-
If the activity addition had occurred within the PERT chart, the PERT chart of the Open_Clamp.1 activity
would subsequently show one
activity as a child.
|
|
|
Insert a Child Activity with a Resource as Parent
|
|
Insert Activity
enables you to assign activities to resources. In order to assign
these resources in V5, they must demonstrate a specific behavior, e.g.,
for the DPE plantypes line and station.
In order to assign activities to resources in V5, you
must have first created a project in DPE, and then open it in V5. The
plantypes line and station have already been configured to correspond to
the plantype set in the R17 release. It is on this basis that you can
create the plantypes line and station resources in V5.
These are the only resources in the tree that can
have activities assigned to them. In the case that a resource has been
selected for execution of Insert Activity
, but cannot
demonstrate this behavior, then the portion of the tree above the
selected resource in the opened project is searched:
-
If a resource is found in the tree, that
demonstrates the behavior, then the activity is assigned to this
resource. The Process uses Resource relation automatically links
processes with a resource.
-
Insert Activity
cannot be executed if a
resource is not found.
A parent/child relationship exists between resources and
activities.activities can only be assigned to resources as children –
Add
as Child must be selected in the Insert Activity dialog
box. |
|
-
Click Insert Activity
in the Activity Management toolbar.
The Insert Activity dialog box appears. |
-
In the Insert Activity dialog box, click Add as Child, if necessary (it is selected by default).
-
Select the activity to
be added as a child activity to your resource.
In the example BIWActivitySpotwelding is selected.In
the example BIWActivitySpotwelding is selected. Note that BIW-Activities
are displayed in the right side of the dialog box. |
 |
-
Select the resource in the tree.
 |
The Create Activity dialog box appears
only for BIW
Activities. This dialog box opens automatically when you assign a BIW
Activity to a resource (as in the example). You can edit
the attributes of the activity in this dialog box. |
|
 |
-
Click OK.
The activity is assigned to the
resource. OK is only available if it is permissible to
assign the activity to the resource. |
 |
|
|
Insert a Successor Activity
|
 |
You cannot add an AssemblyOperation as successor. |
|
-
In the Insert Activity dialog box, click Add
as Successor.
-
In the Insert Activity dialog box, select the
successor activity.
-
On the PPR tree, select the activity that you want the successor activity to follow.
The system responds by adding the activity to the PPR tree
and to the PERT chart (if open). |
If a previously created activity, such as PaintInBlue.1 is selected on the PPR tree, the
newly-created activity follows it. The image below shows PaintInBlue.2
as the successor. |
 |
|
|
Insert
Activities with the PERT Chart
|
|
Use Insert Activity
as described above, but instead of clicking on an
activity in the PPR tree, click on an activity in the PERT chart.
-
If you select Add as Successor, the new activity is added between
the two linked activities.
-
If you select Add as Child, a + (plus) symbol appears in the upper
right corner of the selected parent activity to indicate that the activity has children. Clicking on the +
symbol expands the parent activity to show its children.
|
|
Assign
Products to Activities in Quick Sequence
|
|
The Quick sequence assignment option allows you to create a sequenced set of
operations rapidly, each of which has a product assigned. This option allows you to work around the
task of creating a set of activities, sequencing them, and then
assigning products to each of them one by one. Only activities that can be assigned to a selected object are
displayed in the Insert Activity dialog box. Individual or multiple objects
may be selected in the PPR tree. You first select the PPR object and then open the
Insert
Activity dialog. The dialog box displays only activities that can
actually be assigned to the selected PPR object.
When selecting several
objects at a time, be sure that the selected object types are compatible
with one another. If you select several objects, the program first
checks their compatibility and then opens the dialog. If the objects
selected are not compatible with one another, a message will call
attention to this fact.
If you select several
objects, the option Quick sequence assignment is
automatically pre-selected when you open the dialog box.
|
 |
This method requires that the ProductList of the current PPR
tree already have the desired products loaded into it. |
|
-
Using the Ctrl key, select multiple parts
in the PPR tree. Select the parts in the order you want the
activities associated with them to occur (e.g., if you want the Assembly
Activity for Crankshaft_Assembly to occur before the
Assembly Activity for the Cam_Assembly, then
select Crankshaft_Assembly first.
-
Click Insert Activity
.
-
Select the parent activity (e.g., the Process node) in the PPR tree.
The Insert Activity
dialog box
appears; Quick sequence assignment is available and
selected by default. |
-
In the Insert Activity dialog box, select the activity
you want to assign to the products.
-
Click OK.
This creates the sequence of new activities, with the proper
assignment. |
 |
To see the assigned products in the PPR tree, select
the Items folder / Input Products folder check box in
the Tree tab of Tools > Options > Digital
Process for Manufacturing. |
You can also see the order in the PERT view. |
 |
|
|
Create Logical Activities
|
|
To create logical activities, use the commands on the
Logical Activities toolbar.
Logical activities are created by selecting the required parent activity in the PPR
tree; their position is defaulted inside the PERT chart. Available activity types are:
-
Start
-
Stop
-
OrIn
-
Switch
-
AndIn
-
AndOut
The Switch activity has properties, which can be edited by
right-clicking on the activity in the PERT chart or PPR tree, and
selecting Properties. The properties enable you to
define rules to branch out in the activity flow when an activity has outgoing control flow.
|
|
About Start and Stop Activities
|
|
- The display of the Start and Stop activities in the PPR tree may be turned on or off via the Tools>
Options> Digital Process for Manufacturing> Tree options.
- Start and Stop activities may be automatically created, depending upon the conditions described below.
For Start activities:
- If an activity is pointed to by a control flow, a Start activity is automatically created at the child
level when adding the first child to the activity.
- If an activity has children and a control flow is created which points to the activity, a
Start activity is
automatically created at the child level if it does not already exist.
For Stop activities:
|